PE3 Blue Light Innovation
No classification published
Location not published
Published value
Not published
Submission deadline Not published
Lots published1
Procurement Executive Summary
AI & Search Synopsis
Generated from official OCDS record
Tenderline Synopsis: UK Power Networks (Operations) Limited: "PE3 Blue Light Innovation". Published status: complete. Published value: Value not published. 1 published lot. Submission deadline not published. See the official notice for participation instructions.
| Contracting Authority | UK Power Networks (Operations) Limited | Scope & Categories | Not published | Submission Window | complete No deadline published |
|---|---|---|---|---|---|
| Submission Gateway | Direct notice route | Legal Basis & Regime | Standard procurement | Estimated Value (exc. VAT) | Not published |
Bidder Intelligence · Authority Profile: UK Power Networks (Operations) Limited
Market Analytics
Derived from OCDS awards & bid statistics
Published history for UK Power Networks (Operations) Limited. These figures describe retained records, not a forecast of bids or a measure of buyer bias.
Published-to-award variance
Not availableInsufficient comparable data
Competition Density
Not availableNo published reports
Supplier ConcentrationHigh Concentration
ORACLE CORPORATION UK LTDTop vendor: 74.8% of attributable valuePayment Terms
Check noticePublished terms
Coverage: 8 active published awards; 0 bid reports (which may be per lot). Supplier values exclude multi-supplier awards, frameworks and DPS, and use GBP only. They are published award values, not payments. Published-to-award variance compares single-lot, single-award, single-supplier GBP procedures with explicitly non-framework/non-DPS status; increases remain in the average. Unpublished data stays unknown. Awarded suppliers are winners, not all bidders.
Historical Awarded Suppliers With This Authority:
| Supplier Name | Historic Awards | Attributable GBP Value |
|---|---|---|
| ORACLE CORPORATION UK LTD | 1 win | £3,412,853 |
| J.B. RAWCLIFFE & SONS LIMITED | 1 win | £670,000 |
| National Grid electricity Transmission Plc | 1 win | £476,949 |
Procedure terms
Contracting AuthorityUK Power Networks (Operations) Limited | Procedure methodNot published | Procurement categoryNot published |
Statuscomplete | Framework / DPSNot published | CompetitionNot published |
Above thresholdNot published | Legal basisNot published | Tender period startsNot published |
Clarification deadlineNot published | Electronic submissionNot published | Submission languagesNot published |
Published12 Feb 2026, 17:03 GMT | Last source update12 Feb 2026, 17:03 GMT | Recurring procurementNot published |
ClassificationNot published | ||
Delivery areaLocation not published | ||
OCIDocds-h6vhtk-0646f8 | ||
What is being bought
This requirement is for the delivery of a production-ready digital planning tool that enables emergency services (Police, Fire and Rescue, and Ambulance Trusts) to effectively plan and deliver the decarbonisation of their vehicle fleets and operational estates.
The solution must support strategic electrification planning, improve visibility of electricity network headroom, and reduce the likelihood of unnecessary or premature network reinforcement, while embedding the operational resilience requirements unique to blue light organisations.
The requirement builds directly on the outputs of the completed Phase 1 innovation activity, which validated user need, defined functional and non-functional requirements, and produced tested wireframes and user journeys with engagement from over 60 emergency service organisations. The scope of this commission is therefore delivery focused, translating those agreed designs into an operational system rather than rerunning discovery or design activity.
Core Functional Requirements:
The supplier is required to deliver a minimum viable product (MVP) that provides an endto-end planning journey for a defined set of emergency service sites, including:
- A guided workflow enabling users to model fleet electrification, estate electrification, and associated load impacts.
- Visibility of site-level electrical capacity and network headroom, including constraint indicators and reinforcement triggers.
- Scenario modelling to assess different decarbonisation pathways, including:
- ICE-to-EV fleet replacement logic, charger sizing and charging profiles.
- Specialist vehicle considerations.
- Heat pump, solar PV, battery storage and smart charging options.
- Indicative costs, timescales, and lead-time estimates to support funding, business case development, and connection decisions.
- Portfolio-level aggregation to support roadmap development and prioritisation (post-MVP expansion).
Technical and Delivery Requirements :
The solution must:
-Be delivered as a logically separate, multi-tenanted application built on the existing UKPN ChargePoint Navigator platform and infrastructure, enabling interaction with UKPN systems such as Smart Gateway, NetMap, Autoquote and connection application services.
- Configure and extend existing backend services, data models and APIs to operationalise the agreed wireframes.
- Integrate multiple datasets, including estate data, fleet data, and network capacity information, with appropriate validation, error handling and feedback mechanisms.
- Comply with UK Power Networks' cybersecurity, information governance, and Azure hosting requirements, including agreed authentication and SSO arrangements.
- Be designed from the outset for replication, scale, and transition to business-as-usual (BAU)
The MVP must be production-ready by March 2026 to meet project and customer timelines and to generate evidence for wider rollout decisions.
What changed
From the official release history
- Official notice release published
12 Feb 2026, 17:03 GMT - Status changed to complete
4 Feb 2026, 13:32 GMT - Official notice release published
4 Feb 2026, 13:32 GMT - Buyer information updated
4 Feb 2026, 13:32 GMT
Lots and requirements (1)
Published by the contracting authority
- Lot 1 · #1Individual lot title not publishedcompletePublished valueNot publishedThe source published no individual title or description for this lot.Contract periodNot publishedEligibilityNot publishedOptions / renewalNot published
Timeline
- Procedure published
12 Feb 2026, 17:03 GMT - Award pending
12 Feb 2026, 00:00 GMT · £450,000
Commercial outcome and competition
Awards DOTTED EYES SOLUTIONS LIMITED £450,000 · 12 Feb 2026, 00:00 GMT · pending |
ContractsNo contract published |
Bid statisticsNo aggregate bid statistics published |
Buyer and organisations in this procedure
UK Power Networks (Operations) Limited
Contracting authority GB-COH-03870728Award and contract changes
Documents (0)
Official links; attachments are not copied
No linked documents are published
Related procedures (0)
No related procedures published
Planning and rationale
Planning budgetNot published |
No-engagement rationaleNot published |
Procedure rationaleSchedule 5, paragraph 5 of PA23 applies: The following conditions are met in relation to the public contract:
(a)due to a particular supplier having intellectual property rights or other exclusive rights, only that supplier can supply the goods, services or works required, and
(b)there are no reasonable alternatives to those goods, services or works.
Schedule 5, paragraph 6 of PA23 applies: The following conditions are met in relation to the public contract:
(a)due to an absence of competition for technical reasons, only a particular supplier can supply the goods, services or works required, and
(b)there are no reasonable alternatives to those goods, services or works.
Schedule 5, paragraph 7 of PA23 applies: The following conditions are met in relation to the public contract:The public contract concerns the supply of goods, services or works by the existing supplier which are intended as an extension to, or partial replacement of, existing goods, services or works in circumstances where-
(a)a change in supplier would result in the contracting authority receiving goods, services or works that are different from, or incompatible with, the existing goods, services or works, and
(b)the difference or incompatibility would result in disproportionate technical difficulties in operation or maintenance. |