Operated Plant Framework · UK public procurement notice
Authority: Cumberland Council (Local council)
What is being bought5 lots · detail below
Published requirement descriptionThe Council wishes to procure a framework for the hire of a range of operated plant to support an in-house delivery model of highway maintenance.
All plant must meet the appropriate requirements of the Specification set out in Schedule 4 of the framework agreement and the rates submitted must be inclusive of delivery and travel time to the local depot or to site and should include for all reasonable associated equipment such as a variety of buckets, trailers etc.
CPV: Hire of construction and civil engineering machinery and equipment with operator · Hire of industrial vehicles with driver · Road sweepers
How this framework works
From the published notice- Type
- Closed framework
- Call-offs
- every call-off is a further competition among the appointed suppliers
- Bids received
- 6 bids on the busiest of 4 lots · 5 suppliers appointed
- Framework period
- 4 yrs from 1 Jan 2026
Published description of the framework
If a Framework User decides to hire Operated Plant through this Agreement it may order those Operated Plant set out in Schedule 3 of the framework agreement in accordance with the terms laid down in this Agreement and as more particularly described in clauses 8.2 to 8.7.
8.2 The Framework User shall identify the highest ranked supplier for the item(s) the Framework User wishes to order using the following approach:
8.2.1 The Framework User identifies the relevant Lot based on location within which the Plant is required and the relevant Sub-lot based on the item(s) of plant required.
8.2.2 Subject to Schedule 7 and any suspensions issued under it, the Framework User issues, to all suppliers on the identified Sub-lot, a notice outlining the item(s) of Plant required, the start date, delivery location and the duration of the order.
8.2.3 The notice shall identify the number of days within which the suppliers need to respond. Failure to respond by the specified date means a supplier will not be considered.
8.2.4 Suppliers in their responses must confirm the availability of the identified Plant and include the Proposed Operator's Detail for each item of Plant required.
8.2.5 The score for the supplier for each specific order is identified by adding the Operator Assessment Score and the Price Score and then multiplying the total by the KPI Factor.
8.2.6 The Proposed Operator's Detail is assessed by the Framework User in line with the Operator Assessment Scoring in order to produce an Operator Assessment Score.
8.2.7 The price for the item(s) of plant is taken from Schedule 4 of the Agreement and the price score is calculated using the formula; (lowest cost / cost) * maximum possible score (600).
8.2.8 The KPI Factor is taken from the latest KPI score available at the date of the response. If no KPI score is available the KPI score is assumed as 100.
8.2.9 The supplier with the highest overall score is awarded the Order.
8.3 The Authorised Officer shall issue the Order to the highest ranked supplier, identified by the process outlined at 8.2;
8.4 The Order issued constitutes an offer by the Framework User to hire the Operated Plant identified in accordance with this Agreement.
8.5 Following receipt of an Order, the Supplier shall in the period determined by the Framework User and notified to the Supplier in writing at the same time as the submission of the Order or, in the absence of such notification, within one (1) Business Day of the
date of the Order acknowledge receipt of the Order and either:
8.5.1 notify the Framework User that it declines to accept the Order; or
8.5.2 notify the Framework User that it accepts the Order by signing and returning the Order.
8.6 If the Supplier:
8.6.1 notifies the Framework User that it declines to accept an Order; or
8.6.2 fails to accept the Order in the time-limit referred to in clause 8.5
then the offer from the Framework User to the Supplier shall lapse.
8.7 Where the supplier first approached by the Framework User (as appropriate) under clause 8.2 does not accept an Order or clause 8.4 applies, the Framework User may, at its utmost discretion approach the next highest ranked supplier within the relevant Lot, repeat the process or enter into appropriate arrangements with other suppliers outside of the Agreement.
Lots and requirements (5)Procurement structure
5 lots · all with a published value · same evaluation weights on every lotEvery one of these 5 lots carries the same published figure, £4,700,000: it is the framework's maximum for the whole notice, not each lot's own budget, and no share per lot is published. The cards below say ceiling above rather than repeat it.
Lot #1Lot A - General WagonsAwardedceiling above
Operated - 18 Tonne G.V.W Tipper - Insulated
Operated - 18 Tonne G.V.W Tipper
Operated - 7.5 Tonne G.V.W Tipper
Operated - 26 Tonne G.V.W Tipper
Operated - 26 Tonne G.V.W Tipper - Insulated
Operated - 18 Tonne G.V.W Tipper c/w hiab Clam Shell Bucket
Operated - 26 Tonne G.V.W Tipper c/w hiab Clam Shell Bucket
Operated - 3 cubic meter capacity Gritter
Operated - 6 cubic meter capacity Gritter (With plough as an addition )
Operated - 9 cubic meter capacity Gritter (with plough as an addition )
Operated - 4 Tonne Hotbox
Operated - 9 Tonne Hotbox
Operated - 18 Tonne Hotbox
Operated - 26 Tonne Hotbox
Operated - Articulated Tipper
Operated - Articulated Low Loader
Lot #2Lot B - Tractor, Loaders & ExcavatorsAwardedceiling above
Operated - Tractor Loader Digger 3CX
Operated - Cold Planing Machine - 0.25m - 0.30m Drum
Operated - Tractor Loader Digger 4CX
Operated - 5.0 Tonne Mini Hydraulic Excavator (Tracked)
Operated - Pecker Attachment to fit 5.0 Tonne Mini Hydraulic Excavator
Operated - Pecker Attachment to fit Tractor Loader Digger 3CX
Operated - Pecker Attachment to fit Tractor Loader Digger 4CX
Operated - 1.5 Tonne Mini Hydraulic Excavator (Tracked)
Operated - Pecker Attachment to fit 1.5 Tonne Mini Hydraulic Excavator
Operated - 2.5 Tonne Mini Hydraulic Excavator (Tracked)
Operated - Pecker Attachment to fit 2.5 Tonne Mini Hydraulic Excavator
Operated - 7 Tonne Mini Hydraulic Excavator (Tracked)
Operated - Pecker Attachment to fit 7 Tonne Mini Hydraulic Excavator
Operated - 12 Tonne Standard Hydraulic Excavator (Tracked)
Operated - Pecker Attachment to fit 12.0 Tonne Standard Hydraulic Excavator
Operated - 20 Tonne Standard Hydraulic Excavator (Tracked)
Operated - Pecker Attachment to fit 20 Tonne Standard Hydraulic Excavator
Operated - Dumper 1 Tonne High lift
Opearted - Dumper 3 Tonne
Operated - Dumper 6 Tonne
Operated - Dumper 9 Tonne
Lot #3Lot C - Road SweepersAwardedceiling above
Operated - Standard Road Sweeper (over 10t)
Operated - Dual Road Sweeper (over 10t)
Operated - Standard Road Sweeper (under 10t)
Operated - Dual Road Sweeper (under 10t)
Lot #4Lot D - Road Surfacing EquipmentAwardedceiling above
Operated - Paving Machine Up to 2.5m Width
Operated - Paving Machine Up to 5.0m
Operated - Cold Mining Machine Up to 0.5m Width
Operated - Cold Mining Machine Up to 1.0m Width
Operated - Cold Mining Machine Over 1.0m Width
Operated - 120 Roller
Operated - 90 Roller
Operated - 3 Pin Roller
Operated - Bond Coat Sprayer
Operated - Loading Shovel
Lot #5Lot E - Drain Cleaning EquipmentAwardedceiling above
Operated - Gully Tanker Up to 18t (Driver & Operator)
Operated - Vactor Unit (Driver & Operator)
Operated - Recycling Unit (Driver & Operator)
What it takes to wini
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Evaluation split and conditions of participation as published; the tender pack may add morei
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Published award criteria (3)
- Price
- Quality
- Social Value
- Price carries 60 of 100 points: a 10% discount moves about 6 points. This one is won on the number: sharpen the price before polishing the prose.
- “Operated Plant Framework” is a framework: the contest is a place on its panel, not a single contract: each call-off is a further competition, so the pricing contest starts after appointment.
Price arithmetic assumes straight proportional scoring; the tender pack may use another formula.
Procedure terms & legal framework
From the official record- Procedure method
- Open procedure
- Legal basis
- UKPGA · 2023/54 Procurement Act 2023
- Procurement category
- Services
- Notice status
- Awarded
- Procurement threshold
- Above threshold (FTS publication)
- Regulatory regime
- Standard
- Commercial structure
- Framework agreement
- Who may use this agreement
- Not stated in the notice; call-off rights may be limited to the establishing authority
- Competition type
- Competitive procedure
- GPA / WTO covered
- Yes (GPA)
- Recurring procurement
- Unspecified in notice
- First published
- 22 May 2025, 14:24 BST
- Last source update
- 29 Jan 2026, 09:54 GMT
- Award evaluation window
- Submission end – 28 Nov 2025
- Authority reference
DN792231- FTS notice number
2025/S 000-062639- Latest notice
- Contract details notice (UK7)
- Classification (CPV)
- Delivery area
- Official registry OCID
ocds-h6vhtk-051e22Find a Tender
How it was run
Official notice- Appointment period ends
- 3 Nov 2025, 12:00 GMT
- Clarification deadline
- 17 Oct 2025, 12:00 BST
- Electronic submission
- Allowed
- Accepted languages
- en
Suppliers wishing to express an interest and obtain access to the tender documents should go to www.the-chest.org.uk ↗ and click on current opportunities from the navigation area on the left of the screen. On the next screen enter the contract Reference (DN792231) in the box labelled 'contains' then click search. Click on the Blue link for the contract title to view the opportunity.
To express an interest you will need to login. If you are not already registered on the www.the-chest.org.uk ↗ you will need to return to the home page and click on Register. Register free link in the navigation area on the left of the screen. Registration is free of charge and your username and password will be emailed to you.
Timeline
22 May 2025 → 29 Jan 2026 · 10 dates- Planning notice published22 May 2025, 14:24 BST
- Next notice expected1 Jul 2025, 23:59 BST
- Tender notice published383 days ago6 Oct 2025, 16:46 BST
- Clarification questions by372 days ago17 Oct 2025, 12:00 BST
- Admission / appointment period ends355 days ago · period end, not a bid countdown3 Nov 2025, 12:00 GMT
- Award decision expected by330 days ago28 Nov 2025, 23:59 GMT
- Assessment summaries sent318 days ago11 Dec 2025
- Standstill ends306 days ago22 Dec 2025, 23:59 GMT
- Contract starts297 days ago1 Jan 2026
- Latest notice published268 days ago29 Jan 2026, 09:54 GMT
Notice history
11 events · 5 releases on Find a Tender · since 22 May 2025- Pipeline notice published22 May 2025, 14:24 BSTUK1
- Tender notice published6 Oct 2025, 16:46 BSTUK4
- Published value updated to £4,700,0006 Oct 2025, 16:46 BSTwas £10,000,000
- Status changed to active6 Oct 2025, 16:46 BST
- Procurement method changed6 Oct 2025, 16:46 BST
- Deadline published: 3 Nov 2025, 12:00 GMT6 Oct 2025, 16:46 BST
- Tender notice published6 Oct 2025, 16:53 BSTUK4
- Contract award notice published11 Dec 2025, 12:43 GMTUK6
- Status changed to complete11 Dec 2025, 12:43 GMT
- Contract signature expected29 Dec 2025, 23:59 GMTscheduled
- Contract details notice published29 Jan 2026, 09:54 GMTUK7
Published amendments (1)
End date of framework updated
Routine re-releases (5)
- 2025-10: 1 release · 6 Oct 2025
- 2025-05: 1 release · 22 May 2025
Commercial outcome & contract awards
Published awards, contracts and bid statistics, not a forecast£1,400,000 is the framework's published maximum, restated by the publisher on 3 award rows. It is one ceiling, not 3 separate sums, and no share per lot is published; those rows read “ceiling above”.
| Awarded to | Value | Date | Status |
|---|---|---|---|
| Lot 1 · Lot A - General Wagons1 award | |||
| Cubby Construction LtdSME, DSD Construction Ltd, G Lund LtdSME, John Elliot LtdSMELot A (Wagons)1 Jan 2026 – 31 Dec 2029 | ceiling above | 8 Dec 2025 | Awarded |
| Lot 2 · Lot B - Tractor, Loaders & Excavators1 award | |||
| DSD Construction Ltd, G Lund LtdSME, John Elliot LtdSMELot B (Loaders & Excavators)1 Jan 2026 – 31 Dec 2029 | ceiling above | 8 Dec 2025 | Awarded |
| Lot 3 · Lot C - Road Sweepers1 award | |||
| DSD Construction Ltd, John Elliot LtdSMELot C (Sweepers)1 Jan 2026 – 31 Dec 2030 | £320,000 | 8 Dec 2025 | Awarded |
| Lot 4 · Lot D - Road Surfacing Equipment1 award | |||
| Cubby Construction LtdSME, DSD Construction Ltd, Metcalfe Plant Hire LimitedSMELot D (Road Surface Equipment)1 Jan 2026 – 31 Dec 2029 | ceiling above | 8 Dec 2025 | Awarded |
| Lot 5 · Lot E - Drain Cleaning Equipment1 award | |||
| supplier not published | — | 8 Dec 2025 | Awarded |
Contracts
All 3 of these contracts carry the same published figure, £1,400,000, the framework's maximum for the whole notice, not each contract's own value. They are not eleven separate sums.
Contract 1 · Cubby Construction LtdSME, DSD Construction Ltd, G Lund LtdSME, John Elliot LtdSME
- Signed
- 27 Jan 2026
- Value
- ceiling above
- Period
- 28 Jan 2026 – 31 Dec 2029
- Status
- active
Contract 2 · DSD Construction Ltd, G Lund LtdSME, John Elliot LtdSME
- Signed
- 27 Jan 2026
- Value
- ceiling above
- Period
- 28 Jan 2026 – 31 Dec 2029
- Status
- active
Contract 3 · DSD Construction Ltd, John Elliot LtdSME
- Signed
- 27 Jan 2026
- Value
- £320,000
- Period
- 28 Jan 2026 – 31 Dec 2029
- Status
- active
Contract 4 · Cubby Construction LtdSME, DSD Construction Ltd, Metcalfe Plant Hire LimitedSME
- Signed
- 27 Jan 2026
- Value
- ceiling above
- Period
- 28 Jan 2026 – 31 Dec 2029
- Status
- active
Bid statistics published by the authority
| Lot | Bids | SME | VCSE | Valid bid range |
|---|---|---|---|---|
| 1 · Lot A - General Wagons | 4final-stage tenders | 4 | 0 | — |
| 2 · Lot B - Tractor, Loaders & Excavators | 6final-stage tenders | 5 | 0 | — |
| 3 · Lot C - Road Sweepers | 2final-stage tenders | 2 | 0 | — |
| 4 · Lot D - Road Surfacing Equipment | 3final-stage tenders | 3 | 0 | — |
Contracting authority & participating public bodies
Framework contractors & participating bidders
5 commercial parties on the notice- CUBBY CONSTRUCTION LIMITEDFramework contractor
- DSD CONSTRUCTION LIMITEDFramework contractor
- G. LUND LIMITEDFramework contractor
- JOHN ELLIOT LIMITEDFramework contractor
- METCALFE PLANT HIRE LIMITEDFramework contractor
Official documents & specifications (12)
Official links; attachments are not copiedNotices published for this procedure
- Contract details notice Contract details notice on Find a Tender
- Contract details notice Contract details notice on Find a Tender
- Contract details notice Contract details notice on Find a Tender
- Contract details notice Contract details notice on Find a Tender
- Contract award notice Contract award notice on Find a Tender
- Contract award notice Contract award notice on Find a Tender
- Contract award notice Contract award notice on Find a Tender
- Contract award notice Contract award notice on Find a Tender
Show 4 more notices
- Contract award notice Contract award notice on Find a Tender
- Tender notice Tender notice on Find a Tender
- Tender notice Tender notice on Find a Tender
- Pipeline notice Pipeline notice on Find a Tender