What is being bought

manufacture and procurement of a working at height safety system for the Medium Girder Bridge (MGB) sets

Delivery location

UKD3

Categories

Construction work for bridges 45221100Construction work for bridges 45221100

Lot details

Lot 1

manufacture and procurement of a working at height safety system for the Medium Girder Bridge (MGB) sets

Award criteria
Lowest price

What is included

ItemCategoryQuantity
1Construction work for bridgesNot published

Comparable-procurement analytics

Benchmarked against retained Find a Tender procedures with CPV division 45. The category anchor is Construction work for bridges (45221100); this is a deliberately broad market comparator. The comparison is shown at several levels rather than pretending one company or region is always the best benchmark.

Comparison setProceduresReported bids per procedureNamed award suppliersPrice evidence
Market: CPV division 4517,1344 median · 30.2 average (5,652 of 17,134 with a bid count)3.8 average (6,251 of 17,134 with named award suppliers)Not published
Same buyer3Not published1 average (3 of 3 with named award suppliers)Not published
Delivery region: UKD31657 median · 53.5 average (53 of 165 with a bid count)5.7 average (55 of 165 with named award suppliers)Not published

“Reported bids” is an official aggregate, sometimes reported per lot; it is the closest available competition measure. “Named award suppliers” are winners, not all applicants.

Price-outcome signal

Not enough comparable procedures currently publish both a GBP tender value and a usable lowest-valid-bid value to calculate a responsible price-reduction benchmark. Tenderline deliberately does not infer a saving from named award suppliers or from missing award values.

Procurement strategy & market signals

Framework agreementNot published
Dynamic purchasing systemNot published
Competitive procurementNot published
Recurring requirementNot published
Procurement method rationaleThe Operational Infrastructure programme team, part of the UK Ministry of Defence (MOD), intends to place a Contract with WFEL Ltd for the provision of demonstration and manufacture of a working at height safety system for the Medium Girder Bridge (MGB) sets which was not included in the original MGB Manufacture Contract. The length of the contract will be 4 and the value approximately £3.85M. This safety system has become necessary because standard safety equipment and systems of work across all bridge configurations are now required to ensure compliance with current Working at Height legislation (WaH). The current risk to life from a WaH accident during construction of an MGB is a Class C risk. In order to comply with Health and Safety Executive (HSE) legislation based on Cost Benefit Analysis (CBA) the Army (as the employer) must do all they can to reduce the risk of working at height (WaH) to ALARP. The value of these additional works is less than 50% of the value of the consideration payable under the original contract. In accordance with regulation 4 of The Defence and Security Public Contracts (Amendment) (EU Exit) Regulations 2019 (SI 2019/697) this procurement falls to be regulated under the provisions of the Defence and Security Public Contracts Regulations 2011 as amended (in particular by SI 2019/697 and SI 2020/1450). Prior publication of a contract notice in the Official Journal of the European Union is no longer appropriate. It is considered that the award of the contract without prior publication of a contract notice in the UK e-notification service is lawful in accordance with Regulation 16(1)(d)(i) of the Defence and Security Public Contracts Regulations 2011 additional works. These additional works cannot for technical reasons be carried out or provided separately from those under the original contract without major inconvenience to the MOD because the original equipment manufacturer (OEM) has already been contracted through an Assessment Phase Contract to investigate and propose a WAH Safety Solution. The End User (Army) have paid for and reviewed this proposal and are content that it will meet the WaH legislation and wish to proceed with WFEL’s proposed solution which is currently being developed into a prototype ready to trial. Any deviation from this chosen solution will cause a time delay to the introduction of critical safety equipment and be an economic and resource inconvenience to the Authority. Additionally, following a thorough investigation, the Master Data Packs for MGB (containing all the necessary technical information for a competent engineering company to manufacture the bridge sets) are not available to the Authority to provide to a 3rd party. Therefore a 3rd party supplier would need to design and engineer a WaH system from the ground up without access to any of the MGB technical information. This would result in significant design and production line set up costs and carries a performance and quality risk of components being incompatible with the existing MGB system. As WFEL are the OEM for the MGB, they will have no such incompatibility issues. The Cyber Risk Profile for this requirement identified by the Cyber Risk Assessment is Very Low. Reference 600646679.
Rationale classificationsAdditional deliveries by the original supplier ordered under the strict conditions stated in the directive
Special regimeNot published
Covered byNot published
Submission policyNot published
Selection criteriaNot published
Risk detailsNot published

Planning & early market engagement

BudgetNot published
No-engagement rationaleNot published
Planning documents0
Planning milestones0

No planning milestones published.

Related procurements

No linked framework, prior procurement or reprocurement published.

Awards

009853-2022-1

Statusactive
SupplierWFEL Ltd

Contracts

009853-2022-1

Statusactive
Value£3,850,000

Documents & submission route

No documents are published in the current source record.

Source data inventory

Diagnostic view. “Not published” means this current release does not provide a value.

OCIDocds-h6vhtk-032d1a
Latest release ID009853-2022
Latest release timestampWed Apr 13 2022 09:50:46 GMT+0000 (Coordinated Universal Time)
Sourcefind-a-tender
Official notice URLNot published
Tender statuscomplete
Procurement methodlimited
Procurement method detailsNegotiated without publication of a contract notice
Main procurement categoryworks
Above thresholdNot published
Legal basis32009L0081
Tender period: startNot published
Tender period: endNot published
Expression of interest deadlineNot published
Enquiry deadlineNot published
Award period: startNot published
Award period: endNot published
Submission method detailsNot published
Submission languagesNot published
Electronic catalogue policyNot published
Total tender valueNot published
Tender lots in source1
Tender items in source1
Tender documents in source0
Awards in latest release1
Contracts in latest release1
Parties in latest release3

Notice history

DateEventReference
13 Apr 2022award, contract009853-2022

All source data

Unmodified official OCDS data retained by Tenderline for this procurement process.

Complete current OCDS release JSON
{
  "id": "009853-2022",
  "tag": [
    "award",
    "contract"
  ],
  "date": "2022-04-13T10:50:46+01:00",
  "ocid": "ocds-h6vhtk-032d1a",
  "buyer": {
    "id": "GB-FTS-5483",
    "name": "Ministry of Defence"
  },
  "awards": [
    {
      "id": "009853-2022-1",
      "status": "active",
      "suppliers": [
        {
          "id": "GB-FTS-49922",
          "name": "WFEL Ltd"
        }
      ],
      "relatedLots": [
        "1"
      ],
      "hasSubcontracting": true
    }
  ],
  "tender": {
    "id": "ocds-h6vhtk-032d1a",
    "lots": [
      {
        "id": "1",
        "hasOptions": false,
        "description": "manufacture and procurement of a working at height safety system for the Medium Girder Bridge (MGB) sets",
        "awardCriteria": {
          "criteria": [
            {
              "name": "Lowest price",
              "type": "price"
            }
          ]
        }
      }
    ],
    "items": [
      {
        "id": "1",
        "relatedLot": "1",
        "deliveryAddresses": [
          {
            "region": "UKD3"
          }
        ],
        "additionalClassifications": [
          {
            "id": "45221100",
            "scheme": "CPV",
            "description": "Construction work for bridges"
          }
        ]
      }
    ],
    "title": "MGCC Working at Height",
    "status": "complete",
    "legalBasis": {
      "id": "32009L0081",
      "scheme": "CELEX"
    },
    "description": "manufacture and procurement of a working at height safety system for the Medium Girder Bridge (MGB) sets",
    "classification": {
      "id": "45221100",
      "scheme": "CPV",
      "description": "Construction work for bridges"
    },
    "procurementMethod": "limited",
    "mainProcurementCategory": "works",
    "procurementMethodDetails": "Negotiated without publication of a contract notice",
    "procurementMethodRationale": "The Operational Infrastructure programme team, part of the UK Ministry of Defence (MOD), intends to place a Contract with WFEL Ltd for the provision of demonstration and manufacture of a working at height safety system for the Medium Girder Bridge (MGB) sets which was not included in the original MGB Manufacture Contract. The length of the contract will be 4 and the value approximately £3.85M. This safety system has become necessary because standard safety equipment and systems of work across all bridge configurations are now required to ensure compliance with current Working at Height legislation (WaH). The current risk to life from a WaH accident during construction of an MGB is a Class C risk. In order to comply with Health and Safety Executive (HSE) legislation based on Cost Benefit Analysis (CBA) the Army (as the employer) must do all they can to reduce the risk of working at height (WaH) to ALARP.\nThe value of these additional works is less than 50% of the value of the consideration payable under the original contract.\nIn accordance with regulation 4 of The Defence and Security Public Contracts (Amendment) (EU Exit) Regulations 2019 (SI 2019/697) this procurement falls to be regulated under the provisions of the Defence and Security Public Contracts Regulations 2011 as amended (in particular by SI 2019/697 and SI 2020/1450).  Prior publication of a contract notice in the Official Journal of the European Union is no longer appropriate.  It is considered that the award of the contract without prior publication of a contract notice in the UK e-notification service is lawful in accordance with Regulation 16(1)(d)(i) of the Defence and Security Public Contracts Regulations 2011 additional works.\n\n            \nThese additional works cannot for technical reasons be carried out or provided separately from those under the original contract without major inconvenience to the MOD because the original equipment manufacturer (OEM) has already been contracted through an Assessment Phase Contract to investigate and propose a WAH Safety Solution. The End User (Army) have paid for and reviewed this proposal and are content that it will meet the WaH legislation and wish to proceed with WFEL’s proposed solution which is currently being developed into a prototype ready to trial. Any deviation from this chosen solution will cause a time delay to the introduction of critical safety equipment and be an economic and resource inconvenience to the Authority. Additionally, following a thorough investigation, the Master Data Packs for MGB (containing all the necessary technical information for a competent engineering company to manufacture the bridge sets) are not available to the Authority to provide to a 3rd party. Therefore a 3rd party supplier would need to design and engineer a WaH system from the ground up without access to any of the MGB technical information. This would result in significant design and production line set up costs and carries a performance and quality risk of components being incompatible with the existing MGB system. As WFEL are the OEM for the MGB, they will have no such incompatibility issues.\nThe Cyber Risk Profile for this requirement identified by the Cyber Risk Assessment is Very Low. Reference 600646679.",
    "procurementMethodRationaleClassifications": [
      {
        "id": "D_ADD_DELIVERIES_ORDERED",
        "scheme": "TED_PT_AWARD_CONTRACT_WITHOUT_CALL",
        "description": "Additional deliveries by the original supplier ordered under the strict conditions stated in the directive"
      }
    ]
  },
  "parties": [
    {
      "id": "GB-FTS-5483",
      "name": "Ministry of Defence",
      "roles": [
        "buyer"
      ],
      "address": {
        "region": "UKD3",
        "locality": "Bristol",
        "countryName": "United Kingdom"
      },
      "details": {
        "url": "https://des.mod.uk/",
        "classifications": [
          {
            "id": "MINISTRY",
            "scheme": "TED_CA_TYPE",
            "description": "Ministry or any other national or federal authority, including their regional or local subdivisions"
          },
          {
            "id": "02",
            "scheme": "COFOG",
            "description": "Defence"
          }
        ]
      },
      "identifier": {
        "legalName": "Ministry of Defence"
      },
      "contactPoint": {
        "email": "daisy.wallis106@mod.gov.uk"
      }
    },
    {
      "id": "GB-FTS-49922",
      "name": "WFEL Ltd",
      "roles": [
        "supplier"
      ],
      "address": {
        "region": "UKD3",
        "locality": "Manchester",
        "countryName": "United Kingdom"
      },
      "details": {
        "scale": "large"
      },
      "identifier": {
        "legalName": "WFEL Ltd"
      }
    },
    {
      "id": "GB-FTS-49923",
      "name": "Defence Equipment and Support",
      "roles": [
        "reviewBody"
      ],
      "address": {
        "locality": "BRISTOL",
        "countryName": "United Kingdom"
      },
      "identifier": {
        "legalName": "Defence Equipment and Support"
      }
    }
  ],
  "language": "en",
  "contracts": [
    {
      "id": "009853-2022-1",
      "value": {
        "amount": 3850000,
        "currency": "GBP"
      },
      "status": "active",
      "awardID": "009853-2022-1",
      "dateSigned": "2022-04-13T00:00:00+01:00"
    }
  ],
  "initiationType": "tender"
}
Complete JSON history (1 releases)
13 Apr 2022 · 009853-2022 · award, contract
{
  "id": "009853-2022",
  "tag": [
    "award",
    "contract"
  ],
  "date": "2022-04-13T10:50:46+01:00",
  "ocid": "ocds-h6vhtk-032d1a",
  "buyer": {
    "id": "GB-FTS-5483",
    "name": "Ministry of Defence"
  },
  "awards": [
    {
      "id": "009853-2022-1",
      "status": "active",
      "suppliers": [
        {
          "id": "GB-FTS-49922",
          "name": "WFEL Ltd"
        }
      ],
      "relatedLots": [
        "1"
      ],
      "hasSubcontracting": true
    }
  ],
  "tender": {
    "id": "ocds-h6vhtk-032d1a",
    "lots": [
      {
        "id": "1",
        "hasOptions": false,
        "description": "manufacture and procurement of a working at height safety system for the Medium Girder Bridge (MGB) sets",
        "awardCriteria": {
          "criteria": [
            {
              "name": "Lowest price",
              "type": "price"
            }
          ]
        }
      }
    ],
    "items": [
      {
        "id": "1",
        "relatedLot": "1",
        "deliveryAddresses": [
          {
            "region": "UKD3"
          }
        ],
        "additionalClassifications": [
          {
            "id": "45221100",
            "scheme": "CPV",
            "description": "Construction work for bridges"
          }
        ]
      }
    ],
    "title": "MGCC Working at Height",
    "status": "complete",
    "legalBasis": {
      "id": "32009L0081",
      "scheme": "CELEX"
    },
    "description": "manufacture and procurement of a working at height safety system for the Medium Girder Bridge (MGB) sets",
    "classification": {
      "id": "45221100",
      "scheme": "CPV",
      "description": "Construction work for bridges"
    },
    "procurementMethod": "limited",
    "mainProcurementCategory": "works",
    "procurementMethodDetails": "Negotiated without publication of a contract notice",
    "procurementMethodRationale": "The Operational Infrastructure programme team, part of the UK Ministry of Defence (MOD), intends to place a Contract with WFEL Ltd for the provision of demonstration and manufacture of a working at height safety system for the Medium Girder Bridge (MGB) sets which was not included in the original MGB Manufacture Contract. The length of the contract will be 4 and the value approximately £3.85M. This safety system has become necessary because standard safety equipment and systems of work across all bridge configurations are now required to ensure compliance with current Working at Height legislation (WaH). The current risk to life from a WaH accident during construction of an MGB is a Class C risk. In order to comply with Health and Safety Executive (HSE) legislation based on Cost Benefit Analysis (CBA) the Army (as the employer) must do all they can to reduce the risk of working at height (WaH) to ALARP.\nThe value of these additional works is less than 50% of the value of the consideration payable under the original contract.\nIn accordance with regulation 4 of The Defence and Security Public Contracts (Amendment) (EU Exit) Regulations 2019 (SI 2019/697) this procurement falls to be regulated under the provisions of the Defence and Security Public Contracts Regulations 2011 as amended (in particular by SI 2019/697 and SI 2020/1450).  Prior publication of a contract notice in the Official Journal of the European Union is no longer appropriate.  It is considered that the award of the contract without prior publication of a contract notice in the UK e-notification service is lawful in accordance with Regulation 16(1)(d)(i) of the Defence and Security Public Contracts Regulations 2011 additional works.\n\n            \nThese additional works cannot for technical reasons be carried out or provided separately from those under the original contract without major inconvenience to the MOD because the original equipment manufacturer (OEM) has already been contracted through an Assessment Phase Contract to investigate and propose a WAH Safety Solution. The End User (Army) have paid for and reviewed this proposal and are content that it will meet the WaH legislation and wish to proceed with WFEL’s proposed solution which is currently being developed into a prototype ready to trial. Any deviation from this chosen solution will cause a time delay to the introduction of critical safety equipment and be an economic and resource inconvenience to the Authority. Additionally, following a thorough investigation, the Master Data Packs for MGB (containing all the necessary technical information for a competent engineering company to manufacture the bridge sets) are not available to the Authority to provide to a 3rd party. Therefore a 3rd party supplier would need to design and engineer a WaH system from the ground up without access to any of the MGB technical information. This would result in significant design and production line set up costs and carries a performance and quality risk of components being incompatible with the existing MGB system. As WFEL are the OEM for the MGB, they will have no such incompatibility issues.\nThe Cyber Risk Profile for this requirement identified by the Cyber Risk Assessment is Very Low. Reference 600646679.",
    "procurementMethodRationaleClassifications": [
      {
        "id": "D_ADD_DELIVERIES_ORDERED",
        "scheme": "TED_PT_AWARD_CONTRACT_WITHOUT_CALL",
        "description": "Additional deliveries by the original supplier ordered under the strict conditions stated in the directive"
      }
    ]
  },
  "parties": [
    {
      "id": "GB-FTS-5483",
      "name": "Ministry of Defence",
      "roles": [
        "buyer"
      ],
      "address": {
        "region": "UKD3",
        "locality": "Bristol",
        "countryName": "United Kingdom"
      },
      "details": {
        "url": "https://des.mod.uk/",
        "classifications": [
          {
            "id": "MINISTRY",
            "scheme": "TED_CA_TYPE",
            "description": "Ministry or any other national or federal authority, including their regional or local subdivisions"
          },
          {
            "id": "02",
            "scheme": "COFOG",
            "description": "Defence"
          }
        ]
      },
      "identifier": {
        "legalName": "Ministry of Defence"
      },
      "contactPoint": {
        "email": "daisy.wallis106@mod.gov.uk"
      }
    },
    {
      "id": "GB-FTS-49922",
      "name": "WFEL Ltd",
      "roles": [
        "supplier"
      ],
      "address": {
        "region": "UKD3",
        "locality": "Manchester",
        "countryName": "United Kingdom"
      },
      "details": {
        "scale": "large"
      },
      "identifier": {
        "legalName": "WFEL Ltd"
      }
    },
    {
      "id": "GB-FTS-49923",
      "name": "Defence Equipment and Support",
      "roles": [
        "reviewBody"
      ],
      "address": {
        "locality": "BRISTOL",
        "countryName": "United Kingdom"
      },
      "identifier": {
        "legalName": "Defence Equipment and Support"
      }
    }
  ],
  "language": "en",
  "contracts": [
    {
      "id": "009853-2022-1",
      "value": {
        "amount": 3850000,
        "currency": "GBP"
      },
      "status": "active",
      "awardID": "009853-2022-1",
      "dateSigned": "2022-04-13T00:00:00+01:00"
    }
  ],
  "initiationType": "tender"
}