G7 Airport Infrastructure works funded by Cabinet Office
Site preparation work
Works for complete or part construction and civil engineering work
Published value
Not published
Submission deadline Not published
Lots published1
Procurement Executive Summary
AI & Search Synopsis
Generated from official OCDS record
Tenderline Synopsis: Cornwall Council: "G7 Airport Infrastructure works funded by Cabinet Office". Published status: complete. Published value: Value not published. 1 published lot. Submission deadline not published. See the official notice for participation instructions.
| Contracting Authority | Cornwall Council | Scope & Categories | Not published | Submission Window | complete No deadline published |
|---|---|---|---|---|---|
| Submission Gateway | Direct notice route | Legal Basis & Regime | Standard procurement | Estimated Value (exc. VAT) | Not published |
Bidder Intelligence · Authority Profile: Cornwall Council
Market Analytics
Derived from OCDS awards & bid statistics
Published history for Cornwall Council. These figures describe retained records, not a forecast of bids or a measure of buyer bias.
Published-to-award variance
Not availableInsufficient comparable data
Competition Density
46Bids / Report
Supplier ConcentrationNo estimate
Insufficient attributable awardsNo concentration estimate availablePayment Terms
Check noticePublished terms
Coverage: 383 active published awards; 381 bid reports (which may be per lot). Supplier values exclude multi-supplier awards, frameworks and DPS, and use GBP only. They are published award values, not payments. Published-to-award variance compares single-lot, single-award, single-supplier GBP procedures with explicitly non-framework/non-DPS status; increases remain in the average. Unpublished data stays unknown. Awarded suppliers are winners, not all bidders.
Procedure terms
Contracting AuthorityCornwall Council | Procedure methodNot published | Procurement categoryNot published |
Statuscomplete | Framework / DPSNot published | CompetitionNot published |
Above thresholdNot published | Legal basisNot published | Tender period startsNot published |
Clarification deadlineNot published | Electronic submissionNot published | Submission languagesNot published |
Published24 May 2021, 15:35 BST | Last source update24 May 2021, 15:35 BST | Recurring procurementNot published |
ClassificationSite preparation work, Works for complete or part construction and civil engineering work | ||
Delivery area | ||
OCIDocds-h6vhtk-02b467 | ||
What is being bought
Ground works required at Newquay Airport Cornwall to support the G7 conference:
The key deliverables within this project are:
• Design
• Concrete and Apron Works
• AGL lighting
• High Mast Lighting
• Foul Sewer Solution
• Surfacing
What changed
From the official release history
- Status changed to complete
24 May 2021, 15:35 BST - Official notice release published
24 May 2021, 15:35 BST - Buyer information updated
24 May 2021, 15:35 BST
Lots and requirements (1)
Published by the contracting authority
- Lot 1 · #1Individual lot title not publishedcancelledPublished valueNot publishedGround works required at Newquay Airport Cornwall to support the G7 conference: The key deliverables within this project are: • Design • Concrete and Apron Works • AGL lighting • High Mast Lighting • Foul Sewer Solution • Surfacing Additional information: This work is being carried out in preparation for the G7 summit at Cornwall Airport Newquay, and has been agreed and funded by the Cabinet OfficeContract periodNot publishedEligibilityNot publishedOptions / renewalNot published
Timeline
- Procedure published
24 May 2021, 15:35 BST - Award active
Not published · Not published - Contract active
Signed 26 Mar 2021, 00:00 GMT · £7,074,641
Commercial outcome and competition
Awards Cormac Solutions Ltd Not published · Not published · active |
Contracts G7 Airport Infrastructure works funded by Cabinet Office £7,074,641 · signed 26 Mar 2021, 00:00 GMT · active |
Bid statistics bids: 1 (lot 1) |
Buyer and organisations in this procedure
Cornwall Council
Contracting authority GB-FTS-215Documents (0)
Official links; attachments are not copied
No linked documents are published
Related procedures (0)
No related procedures published
Planning and rationale
Planning budgetNot published |
No-engagement rationaleNot published |
Procedure rationaleThis work is required to be completed under extreme urgency in preparation for the G7 Summit
Cornwall Council has followed its contract procedure rules and has awarded this contract to Cormac Solutions Ltd via an internal direct award, The works are within Cormac's remit as part of Cornwall Councils Group Of Companies. The Cabinet office are funding these works and have agreed this procurement route. |