Find a TenderClosedTender notice
Published 9 May 2025, 15:49 BST

Official UK procurement notice

DN773397 The Complete Rewire, Replacement of Mechanical Services and Building Works of the Key Stage 1 Building at Manorbrook Primary School, Thornbury

Official notice

Authority: South Gloucestershire Council (Local council)

WorksBelow threshold - open competitionBelow threshold
Sectors: Construction & Civil Engineering (45) Delivery: Delivery location not published
Published estimate£600,000£720,000 inc. VAT
Submissions closed 30 May 2025
Contract term 2 moends 1 Sept 2025 · starts 5 Jul 2025

What is being bought

Published requirement description

The Council is seeking to appoint an NICEIC Approved Electrical Contractor to act as Principal Contractor with the capability and experience to manage specialist sub-contractors to undertake and execute the following works during the school summer holiday period (7th July – 31st August 2025) at Manorbrook Primary School, Park Road, Thornbury, BS35 1JW:

(i) the complete rewire, replacement of heating pipework, heat emitters, individual room ventilation systems, hot and cold-water services pipework (not including the main boiler plant) and associated building works which includes minor building adaptations, replacement of suspended ceilings, replacement of required flooring and complete redecoration in the Key Stage 1 (KS1) building.

(ii) undertake minor building adaptations in the stand-alone Key Stage 2 (KS2) building (which includes changing the use of the staff room into a library).

(iii) construct a new external concrete base for future outdoor building.

(iv) remove the furniture and education resource materials from the KS1 into specific areas of the adjacent KS2 building at the beginning of the school holiday from Saturday 19th July before the works commence and return the furniture at the end of the contract 30th and 31st August 2025 (as detailed in Schedule 3.5).

(v) carry out a through professional service clean of the work areas in the KS1 and KS2 before return of furniture towards the end of the contract (as detailed in Schedule 3.6).

The Council will not consent to the whole of the works being sub-contracted. It is essential that this project is successfully executed during the summer recess so the Contractor will need to demonstrate they have recently completed at least one similar project successfully (similar scope of work, similar value and similar timescale) and they have the competency and sufficient resources to meet these deadlines.

The Contractor shall appoint a competent and suitably experienced full-time site-based representative (i.e. site supervisor /contract manager) throughout the duration of the contract works. It is expected the contractor will have to work longer weekdays and weekends to complete the work within the contract period and include these costs in their tender.

The whole of the works shall be carried out in accordance with the terms and conditions of the JCT Standard Building Contract without quantities 2016 (SBC/XQ), published on behalf of The Joint Contracts Tribunal Limited by Thomson Reuters (Legal) Limited trading as Sweet & Maxwell. The Contractor shall obtain a copy of The Joint Contracts Tribunal Limited Minor Works Building Contract 2016 and shall make themself aware of the conditions therein.

On the accompanying Architect’s drawings, these works are described as ‘phase 1’, as this is the initial stage to increase the capacity of the school over the new few years.

The Key Stage 1 building is a single storey flat roof SCOLA type building built in the 1970’s of 873m2 gross internal floor area. The Key Stage 2 building (1212m2), of the similar age as KS1 is part single and part two-storey. The standalone boiler room houses the centralised heating and hot water plant which serves both buildings.

The works shall be carried out in accordance with the Construction (Design and Management) Regulations 2015. The Contractors will need to demonstrate they are fully conversant with their responsibilities under the Regulations in their tender return and allow for all costs associated with their management of the Contract. The council has appointed a CDM Advisor who has produced the Health & Safety Pre-construction information given in Schedule 7.

There has been a previous lighting replacement scheme with LED luminaires provided to the majority of the areas and these shall be carefully removed, stored, reinstated and incorporated into the proposed circuits with new controls and emergency lighting.

The Principal Contractor shall be responsible for arranging and managing the temporary decanting of furniture from all rooms in KS1 into the adjacent KS2 building (in rooms shown on contract drawings) by a specialist commercial removal specialist. This shall include supply commercial stackable crates, large trolleys to move larger bulky item (e.g. materials and sports equipment) and moving large PE equipment. The Contractor shall appoint and instruct the removal specialist to deliver packaging crates from the date of appointment to enable the school to pack away all loose educational equipment into the crates and trolleys. The Council will arrange the removal and refixing of the interactive whiteboards.

A school summer holiday club will operate from part of the KS2 building. The contract information shows required Heras fencing and describes the sequence of works needed to ensure there is a clear barrier between the contractor’s working area and the holiday club.

Contractors shall ensure they can meet the required ‘pass’ criteria questions in ITT Schedule 2 (PSQ) before preparing and submitting a tender.

CPV: Electrical installation work

The lotProcurement structure

single lot · value published
Lot #1 2 moPublished value£600,000
Contract period: 5 Jul 2025 – 1 Sept 2025 (2 mo)Value: £600,000 exc. VAT · £720,000 inc. VAT

What it takes to win
i

How this buyer will score bids.

The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).

Evaluation split and conditions of participation as published; the tender pack may add more
How bids were scored

Lot awarding rule: below threshold evaluation

Procedure terms & legal framework

From the official record
Procedure method
Below threshold - open competition
Legal basis
UKPGA · 2023/54 Procurement Act 2023
Procurement category
Works
Notice status
Closed
Procurement threshold
Below threshold
Regulatory regime
Standard
Commercial structure
Stand-alone contract (no framework)
Competition type
Competitive procedure
GPA / WTO covered
Unspecified in notice
Recurring procurement
Unspecified in notice
First published
9 May 2025, 15:49 BST
Last source update
9 May 2025, 15:49 BST
Authority reference
DN773397
FTS notice number
2025/S 000-020162
Latest notice
Tender notice (UK4)
Classification (CPV)
Electrical installation work
Delivery area
Not published
Official registry OCID
ocds-h6vhtk-051000 Find a Tender

How it was run

Official notice
Run through: portal not identified
Electronic submission allowed
Submission deadline
30 May 2025, 14:00 BST
Submission channel
Official e-sourcing portal
Electronic submission
Allowed
Detailed submission instructions & authority contactsFrom official release

Timeline

9 May 2025 → 5 Jul 2025 · 3 dates
  1. Tender notice published
    9 May 2025, 15:49 BST
  2. Submission deadline
    30 May 2025, 14:00 BST
  3. Contract starts
    5 Jul 2025

Notice history

1 event · 1 release on Find a Tender
  1. Tender notice published
    9 May 2025, 15:49 BST
    UK4

Contracting authority & participating public bodies

South Gloucestershire Council

Contracting authorityPublic authority - sub-central government GB-PPON: PCMC-1241-BLJQ Council Offices, Badminton Road, Yate, South West, BS37 5AFContact name, email, phone

Official documents & specifications (1)

Official links; attachments are not copied

Notices published for this procedure

  • Tender notice tenderTender noticeUK4Tender notice on Find a Tender