Wightfibre Circuits - direct internet connection at St Mary’s datacentre
IT services: consulting
software development
Internet and support
+1 more
Published value
Not published
Submission deadline Not published
Lots published1
Procurement Executive Summary
AI & Search Synopsis
Generated from official OCDS record
Tenderline Synopsis: Isle of Wight Council: "Wightfibre Circuits - direct internet connection at St Mary’s datacentre". Published status: complete. Published value: Value not published. 1 published lot. Submission deadline not published. See the official notice for participation instructions.
| Contracting Authority | Isle of Wight Council | Scope & Categories | Not published | Submission Window | complete No deadline published |
|---|---|---|---|---|---|
| Submission Gateway | Direct notice route | Legal Basis & Regime | Standard procurement | Estimated Value (exc. VAT) | Not published |
Bidder Intelligence · Authority Profile: Isle of Wight Council
Market Analytics
Derived from OCDS awards & bid statistics
Published history for Isle of Wight Council. These figures describe retained records, not a forecast of bids or a measure of buyer bias.
Published-to-award variance
Not availableInsufficient comparable data
Competition Density
3.1Bids / Report
Supplier ConcentrationNo estimate
Insufficient attributable awardsNo concentration estimate availablePayment Terms
Check noticePublished terms
Coverage: 106 active published awards; 90 bid reports (which may be per lot). Supplier values exclude multi-supplier awards, frameworks and DPS, and use GBP only. They are published award values, not payments. Published-to-award variance compares single-lot, single-award, single-supplier GBP procedures with explicitly non-framework/non-DPS status; increases remain in the average. Unpublished data stays unknown. Awarded suppliers are winners, not all bidders.
Procedure terms
Contracting AuthorityIsle of Wight Council | Procedure methodNot published | Procurement categoryNot published |
Statuscomplete | Framework / DPSNot published | CompetitionNot published |
Above thresholdNot published | Legal basisNot published | Tender period startsNot published |
Clarification deadlineNot published | Electronic submissionNot published | Submission languagesNot published |
Published6 Nov 2024, 11:16 GMT | Last source update6 Nov 2024, 11:16 GMT | Recurring procurementNot published |
ClassificationIT services: consulting, software development, Internet and support, Software package and information systems | ||
Delivery area | ||
OCIDocds-h6vhtk-04b43f | ||
What is being bought
1 x 500Mbps direct internet connection at St Mary’s datacentre
What changed
From the official release history
- Status changed to complete
6 Nov 2024, 11:16 GMT - Official notice release published
6 Nov 2024, 11:16 GMT - Buyer information updated
6 Nov 2024, 11:16 GMT
Lots and requirements (1)
Published by the contracting authority
- Lot 1 · #1Individual lot title not publishedcancelledPublished valueNot published1 x 500Mbps direct internet connection at St Mary’s datacentre May 2024 - April 2025 (with 12m extension possible to April 2026) Cost includes whole life cost (12m + 12m).Contract periodNot publishedEligibilityNot publishedOptions / renewalNot published
Timeline
- Procedure published
6 Nov 2024, 11:16 GMT - Award active
Not published · Not published - Contract active
Signed 30 Apr 2024, 00:00 BST · £12,000
Commercial outcome and competition
Awards Wight Fibre Not published · Not published · active |
Contracts Contract £12,000 · signed 30 Apr 2024, 00:00 BST · active |
Bid statistics bids: 1 (lot 1) |
Buyer and organisations in this procedure
Isle of Wight Council
Contracting authority GB-FTS-67Documents (0)
Official links; attachments are not copied
No linked documents are published
Related procedures (0)
No related procedures published
Planning and rationale
Planning budgetNot published |
No-engagement rationaleNot published |
Procedure rationale1 x 500Mbps direct internet connection at St Mary’s datacentre, May 2024 - April 2025 (with 12m extension possible to April 2026).
The supplier (Wight Fibre) has its own Island Infrastructure already in situ; any other supplier would depend on utilising Open Reach infrastructure to supply our requirements, which in itself carries a higher cost than is offered by Wight Fibre, whose infrastructure is already in place. A cost comparison with another provider was carried out with Wight Fibre as lowest cost, but with additional benefits such as monitoring of real time bandwidth and traffic usage. Wight Fibre’s offering also includes a large number of public IP addresses on two of the direct internet connections, upstream DNS mirroring, built in resilience, 24/7 365 days a year coverage for faults, monitoring, and reporting.
Continuity of supply of our connection(s) is of high importance and as well as the cost
effectiveness mentioned.
The Isle of Wight Council observed a 10-day standstill period which ended at
midnight on 04 November 2024. |