Rochester Airport Additional Works Package
Construction work
Published value
Not published
Submission deadline Not published
Lots published1
Procurement Executive Summary
AI & Search Synopsis
Generated from official OCDS record
Tenderline Synopsis: Medway Council: "Rochester Airport Additional Works Package". Published status: complete. Published value: Value not published. 1 published lot. Submission deadline not published. See the official notice for participation instructions.
| Contracting Authority | Medway Council | Scope & Categories | Not published | Submission Window | complete No deadline published |
|---|---|---|---|---|---|
| Submission Gateway | Direct notice route | Legal Basis & Regime | Standard procurement | Estimated Value (exc. VAT) | Not published |
Bidder Intelligence · Authority Profile: Medway Council
Market Analytics
Derived from OCDS awards & bid statistics
Published history for Medway Council. These figures describe retained records, not a forecast of bids or a measure of buyer bias.
Published-to-award variance
Not availableInsufficient comparable data
Competition Density
20.3Bids / Report
Supplier ConcentrationNo estimate
Insufficient attributable awardsNo concentration estimate availablePayment Terms
Check noticePublished terms
Coverage: 72 active published awards; 66 bid reports (which may be per lot). Supplier values exclude multi-supplier awards, frameworks and DPS, and use GBP only. They are published award values, not payments. Published-to-award variance compares single-lot, single-award, single-supplier GBP procedures with explicitly non-framework/non-DPS status; increases remain in the average. Unpublished data stays unknown. Awarded suppliers are winners, not all bidders.
Procedure terms
Contracting AuthorityMedway Council | Procedure methodNot published | Procurement categoryNot published |
Statuscomplete | Framework / DPSNot published | CompetitionNot published |
Above thresholdNot published | Legal basisNot published | Tender period startsNot published |
Clarification deadlineNot published | Electronic submissionNot published | Submission languagesNot published |
Published28 May 2021, 16:07 BST | Last source update28 May 2021, 16:07 BST | Recurring procurementNot published |
ClassificationConstruction work | ||
Delivery area | ||
OCIDocds-h6vhtk-02b67c | ||
What is being bought
Medway Council procured the initial Rochester Airport works and subsequently awarded a contract to Kier for the sum of £4.3m. During the redevelopment of Rochester Airport unforeseen project challenges have required a change in the project scope for an additional sum of £2.6m resulting in a total project cost of £6.9m.
What changed
From the official release history
- Status changed to complete
28 May 2021, 16:07 BST - Official notice release published
28 May 2021, 16:07 BST - Buyer information updated
28 May 2021, 16:07 BST
Lots and requirements (1)
Published by the contracting authority
- Lot 1 · #1Individual lot title not publishedStatus not publishedPublished valueNot publishedMedway Council procured the initial Rochester Airport works and subsequently awarded a contract to Kier for the sum of £4.3m. During the redevelopment of Rochester Airport unforeseen project challenges have required a change in the project scope for an additional sum of £2.6m resulting in a total project cost of £6.9m.Contract periodNot publishedEligibilityNot publishedOptions / renewalNot published
Timeline
- Procedure published
28 May 2021, 16:07 BST - Award active
Not published · Not published - Contract active
Signed 27 May 2021, 00:00 BST · £2,600,000
Commercial outcome and competition
Awards Kier Construction Not published · Not published · active |
Contracts Contract £2,600,000 · signed 27 May 2021, 00:00 BST · active |
Bid statisticsNo aggregate bid statistics published |
Buyer and organisations in this procedure
Medway Council
Contracting authority GB-FTS-3633Documents (0)
Official links; attachments are not copied
No linked documents are published
Related procedures (0)
No related procedures published
Planning and rationale
Planning budgetNot published |
No-engagement rationaleNot published |
Procedure rationaleMedway Council procured the initial Rochester Airport works and subsequently awarded a contract to Kier for the sum of £4.3m.
Further works were required for an additional contract sum of £2.6 million and therefore the value of this contract is now in excess of the financial threshold and the Public Contract Regulation 2015 (PCR 2015 ) are applicable.
The proposed extension and increase in contract price does not contravene the PCR 2015 which in accordance with Reg 72 (1 ) (e) permits modifications of contracts irrespective of their value provided that the modification is not substantial within the meaning of Reg 72 (8 ).
These additional works are ancillary to the original works and does not constitute a substantial modification because the works do not :
a) extend the scope of the works considerably or;
b) render the contract materially different in character or;
c) change the economic balance of the contract in favour of the contractor in manner not provided for in the initial contract or introduce conditions permitting the admission of candidates or acceptance of tenders or attracting additional participants |