BHS/HRA/Development of Affordable Housing: Care Enabled, Older Persons’ Housing at Blake Centre Site, Lockleaze, Bristol
Construction work
Published value
Not published
Submission deadline Not published
Lots published1
Procurement Executive Summary
AI & Search Synopsis
Generated from official OCDS record
Tenderline Synopsis: Bristol City Council: "BHS/HRA/Development of Affordable Housing: Care Enabled, Older Persons’ Housing at Blake Centre Site, Lockleaze, Bristol". Published status: planned. Published value: Value not published. 1 published lot. Submission deadline not published. See the official notice for participation instructions.
| Contracting Authority | Bristol City Council | Scope & Categories | Not published | Submission Window | planned No deadline published |
|---|---|---|---|---|---|
| Submission Gateway | Direct notice route | Legal Basis & Regime | Standard procurement | Estimated Value (exc. VAT) | Not published |
Bidder Intelligence · Authority Profile: Bristol City Council
Market Analytics
Derived from OCDS awards & bid statistics
Published history for Bristol City Council. These figures describe retained records, not a forecast of bids or a measure of buyer bias.
Average Price Reduction
Not availableInsufficient comparable data
Competition Density
3.7Bids / Report
Supplier ConcentrationNo estimate
Insufficient attributable awardsNo concentration estimate availablePayment Terms
Check noticePublished terms
Coverage: 35 active published awards; 35 bid reports (which may be per lot). Supplier values exclude multi-supplier awards, frameworks and DPS, and use GBP only. They are published award values, not payments. Price reduction compares single-lot, single-award, single-supplier GBP procedures with explicitly non-framework/non-DPS status; increases remain in the average. Unpublished data stays unknown. Awarded suppliers are winners, not all bidders.
Procedure terms
Contracting AuthorityBristol City Council | Procedure methodNot published | Procurement categoryNot published |
Statusplanned | Framework / DPSNot published | CompetitionNot published |
Above thresholdNot published | Legal basisNot published | Tender period startsNot published |
Clarification deadlineNot published | Electronic submissionNot published | Submission languagesNot published |
Published16 Sept 2024, 20:04 BST | Last source update16 Sept 2024, 20:04 BST | Recurring procurementNot published |
ClassificationConstruction work | ||
Delivery area | ||
OCIDocds-h6vhtk-03c23d | ||
What is being bought
BCC wish to appoint a Development Partner, who is a Registered Provider, within the South-West of England, and a HomesWest Partner or, is willing to apply to be a HomesWest Partner via Bristol City Council’s Housing Enabling Team. The selected Development Partner will develop and submit a planning application that will deliver a 100% affordable housing scheme that is designed to provide Care enabled, older persons’ housing at the Blake Centre Site and provide housing management to the newly tenanted homes. The scheme should be designed using HAPPI principles as set out in the Housing our Ageing Population Panel for Innovation (HAPPI) standard, for both the residential dwellings and the (up to) 250 sqm commercial (as per the soon to be expired outline planning consent).
Outline planning permission was granted in 2021 for the delivery of up to 60 dwellings (Use Class C3) and up to 250sqm of flexible commercial floor space (Use Classes E, F1 and F2) with associated car parking, refuse/recycling storage and landscaping. This permission expired on the 13th of September 2024 however, the expectation is that future Full Planning application proposals will be in line with the previously approved plans (ref: 21/01549/P).
Design proposals should future-proof the development by providing a care enabled housing scheme that could provide an ‘Extra Care Housing light’ model, should there be a future requirement from the Council. Any such request from the Council for an ‘Extra Care Housing light’ model at the Blake Centre Site would be agreed through early discussions with the selected Registered Provider prior to changes being implemented.
The Council has undertaken considerable soft market testing with regards to this site (such as 2023/S 000-011315), with no contract being awarded to date due to the lack of interest. The Council is undertaking this final piece of market testing in light of the changes agreed by Homes England. Given that the Council has already completed various market testing processes and attempted to openly tender for the development agreement in 2023, the Council reserves the right to negotiate directly with a provider should no suitable organisations respond to this Expression of Interest. The requirements are detailed within the Expression of Interest document. Providers must be able to demonstrate they meet the requirements; the Council will not accept speculative submissions.
Expected Programme dates agreed with Homes England (March 2024)
Milestones
Full planning consent achieved for housing development of the site: 30/06/2025
Start on site of housing development: 31/10/2025
Start of first housing unit: 30/11/2025
Practical completion: 31/10/2027
Project completion: 30/11/2027
What changed
From the official release history
- Status changed to planned
16 Sept 2024, 20:04 BST - Official notice release published
16 Sept 2024, 20:04 BST - Submission deadline changed to published date
16 Sept 2024, 20:04 BST - Status changed to active
20 Apr 2023, 10:49 BST - Official notice release published
20 Apr 2023, 10:49 BST - Submission deadline changed to 5 Jun 2023, 12:00 BST
20 Apr 2023, 10:49 BST - Buyer information updated
20 Apr 2023, 10:49 BST
Lots and requirements (1)
Published by the contracting authority
- Lot 1 · #1Individual lot title not publishedplannedPublished valueNot publishedBCC wish to appoint a Development Partner, who is a Registered Provider, within the South-West of England, and a HomesWest Partner or, is willing to apply to be a HomesWest Partner via Bristol City Council’s Housing Enabling Team. The selected Development Partner will develop and submit a planning application that will deliver a 100% affordable housing scheme that is designed to provide Care enabled, older persons’ housing at the Blake Centre Site and provide housing management to the newly tenanted homes. The scheme should be designed using HAPPI principles as set out in the Housing our Ageing Population Panel for Innovation (HAPPI) standard, for both the residential dwellings and the (up to) 250 sqm commercial (as per the soon to be expired outline planning consent). Outline planning permission was granted in 2021 for the delivery of up to 60 dwellings (Use Class C3) and up to 250sqm of flexible commercial floor space (Use Classes E, F1 and F2) with associated car parking, refuse/recycling storage and landscaping. This permission expired on the 13th of September 2024 however, the expectation is that future Full Planning application proposals will be in line with the previously approved plans (ref: 21/01549/P). Design proposals should future-proof the development by providing a care enabled housing scheme that could provide an ‘Extra Care Housing light’ model, should there be a future requirement from the Council. Any such request from the Council for an ‘Extra Care Housing light’ model at the Blake Centre Site would be agreed through early discussions with the selected Registered Provider prior to changes being implemented. The Council has undertaken considerable soft market testing with regards to this site (such as 2023/S 000-011315), with no contract being awarded to date due to the lack of interest. The Council is undertaking this final piece of market testing in light of the changes agreed by Homes England. Given that the Council has already completed various market testing processes and attempted to openly tender for the development agreement in 2023, the Council reserves the right to negotiate directly with a provider should no suitable organisations respond to this Expression of Interest. The requirements are detailed within the Expression of Interest document. Providers must be able to demonstrate they meet the requirements; the Council will not accept speculative submissions. Expected Programme dates agreed with Homes England (March 2024) Milestones Full planning consent achieved for housing development of the site: 30/06/2025 Start on site of housing development: 31/10/2025 Start of first housing unit: 30/11/2025 Practical completion: 31/10/2027 Project completion: 30/11/2027Contract periodNot publishedEligibilityNot publishedOptions / renewalNot published
Timeline
- Procedure published
16 Sept 2024, 20:04 BST
Commercial outcome and competition
AwardsNo award published |
ContractsNo contract published |
Bid statisticsNo aggregate bid statistics published |
Buyer and organisations in this procedure
Bristol City Council
Contracting authority GB-FTS-3840Documents (0)
Official links; attachments are not copied
No linked documents are published
Related procedures (0)
No related procedures published